Project Phases
Phase I- Information mapping, evaluation, and project planning
Using JIEM tool, map information exchanges as they exist in Crisp County (Map Complete)
Evaluate information exchange map, and identify crucial exchanges (Warrant/arrest information identified)
Using JIEM tool, develop model for automation system to be installed in Crisp County (Complete)
Select vendor to develop and install temporary Proof of Concept platform (Metatomix selected)
Phase II- Proof of Concept Development
Work with Middleware vendor selected in Phase I to develop integration plan (ongoing throughout phase II)
Demonstrated ability to read database of each participating agency (successful reads of DA, Public Defender, & Magistrate Court)
Demonstrate ability to write to each database of each participating agency (successful writes to DA and Public Defender)
Perform test integration with live data (Complete)
Install integration platform (Installed and running)
Phase III- Proof of Concept Demonstration and Evaluation
Evaluate Proof of Concept Demonstration for 90 day period (Complete)
Identify flaws and corrections to be made for fully operational system (Complete)
Release RFP to qualified vendors (Complete)
Select vendor to install full system
Phase IV- System Operation
Criminal Justice Agencies in Crisp County Use the integration features daily |